Construction 36.3% delay -2.9%
MFSC & Associates 32.8% delay -0.3%
HDPE/mLLDPE 34% delay -3.5%
HDPE-BIMODAL 36.3% delay -2.9%
PP-ICP/HR 37.5% delay -11.7%
Pipe Rack 41.19% delay -12.9%
Waste Water 61.27% delay -5.68%
Water System (E) 70.45% delay -0.5%
Water System (W) 56.8% delay -2.54%
Warehouses 54.65% delay -0.08%
Incinerator 44.04% delay -4.23%
220KV Substation 48.17% delay -3.71%
Off Site 19.72% delay -1.97%
Whole Site 55.82% delay -0.35%
Early Work 99.4% delay -0.63%